A lawn and landscape company · About $18M revenue; 30 crews across 4 branches

A Novare engagement. The client's name is withheld.

Are we on plan this week, and if not, where?

The answer Two branches were running labor about three points over plan. The cockpit showed it in week 2, not at month-end.

  • $240Ka year of labor kept to plan
  • Week 2not five weeks later
  • 1 pageevery Monday

A Novare engagement. The client's name is withheld.

01

The question

Leadership met every Monday, but the numbers they had were five weeks old. By the time the month closed, a bad month was already over. Each branch kept its own spreadsheet, and none of them matched.

  • Budget lived in one file. Actuals lived in the books. Jobs lived in the scheduling system.
  • Each branch manager reported a different version of labor cost.
  • Problems showed up at month-end, too late to fix.

Next: What we looked at

02

What we looked at

We put budget and actuals side by side, by branch and by week, using the same definitions everywhere.

  • Revenue was on budget. Labor was not.
  • Two branches were about three points over plan on labor, from overtime and rework.
  • Nobody had seen it, because nobody was looking at weekly labor by branch.
Labor cost vs. plan, by branch
Branch A+0.4 ptsBranch B+3.2 ptsBranch C−0.6 ptsBranch D+2.9 pts

Labels are generic to keep the client anonymous.

Next: What we built

03

What we built

  1. One set of definitions

    What counts as revenue, labor and a completed job, agreed once and used everywhere.

  2. Weekly budget vs. actual

    Pulled from the books, payroll and scheduling, and checked against the books before anyone sees it.

  3. A one-page cockpit

    Five numbers, every branch, and a short list of what needs attention.

  4. A Monday routine

    Fifteen minutes. Each red item gets an owner and a date.

The Monday cockpit

Next: The answer and the money

04

The answer and the money

Both branches fixed crew sizing and rework within six weeks and got labor back to plan. On about $8M of revenue in those branches, three points is about $240K a year.

Labor in the two over-plan branches: before and after the cockpit
BeforeAfterChange
When a labor overrun showed upMonth-end, with numbers five weeks oldWeek 2Five weeks sooner
Labor vs. plan (2 branches)About three points over planBack to plan within six weeksAbout three points
Annual value—About $240K a year of labor kept to plan≈$240K a year
Labor as a share of revenue, week by week
36%38%40%42%Wk 1Wk 4Wk 8Wk 12PlanBranch BBranch DFlagged in week 2

Labels are generic to keep the client anonymous.

The Monday meeting now starts with the same page for everyone, and it is never more than a week old.

The work behind this story

Systems involved: The budget file, the books, payroll and the scheduling system.

A Novare engagement. The client's name is withheld. Results vary by business. One company's results are not a forecast for another.

Running into a version of this?

Tell us what you’re seeing. We’ll tell you how we’d find the answer and what it would take.

Start a conversation →